Our customer's client had a very short time from the completion of a hosting contract to requiring an operational service.
Once we had suggested a few design changes to ensure the installation would be practical, our engineers installed over 1300 Cat.5e links to interconnect the client's racks.
Agressive timescales from the end client saw our engineers working flat out to beat our planned completion date. With their help we were able to finish the installation and testing in half the time that we'd initially allowed, ensuring the client had sufficient time to install their active equipment before the go-live date.
Posted Date: 17th Mar 2011