Gem engineers installed 200+ Cat.5e outlets in a clients offices in Central London. The installation was carried out alongside the other trades, all working to meet aggressive timescales.
This required a great deal of flexibility in terms of planning, as our engineers would often find their planned route blocked by furniture under construction, or by fitters laying carpet over the raised access floor.
Despite the problems encountered on site, all cabling works for the first fix were completed ahead of schedule, allowing the refurbishment works to be completed in plenty of time for second fix, where the cables were terminated and tested.
The complete install was handed over to the client along with O&M manuals for both the end client and the landlord
Posted Date: 12th Jan 2010